AirTrain Extension & Improvements Program
San Francisco International Airport
San Francisco, CA
MCK provided Cost Estimating and Scheduling services to San Francisco International Airport under the Project Management Support Services contract for the Air Train Extension and Improvements Program.
This $500M project provided design and construction for:
-
Elevated concrete guideway extension of roughly one mile from its current termination point at the Rental Car Center to Lot DD.
-
A new four-car station to serve Lot DD, Long Term Parking Garage No. 2 and the Airport Hotel.
-
Design, installation, testing, and commissioning of related AirTrain Operating System upgrade work and an upgrade from the 2001-era Train Control System to a new technology Line-of-Sight Train Control System for the entire AirTrain operating system.
This project completed in August 2020.